This came up on a LinkedIn discussion group on project management. The
question was whether, in a vendor-driven project, the project manager should
come from the vendor or the client. What follows is my answer. -- Bob
The discussion makes it sound as if having a client project manager and having a
vendor project manager are either/or alternatives. I've been on both sides of
this and have always done my best to insist there be one of each.
[ Also on InfoWorld: "The world's quickest course in project management" | Get
sage advice on IT careers and management from Bob Lewis in InfoWorld's Advice
Line newsletter. ]
This wouldn't be necessary if all project managers were always highly competent
at their jobs. But since they aren't ...
When the vendor project manager is weak, the client needs its own pair of eyes
on things to recognize the problem and insist on a resolution. Take, for
instance, this actual dialog:
Client project manager: When will we see a project plan?
Vendor project manager: We don't usually create project plans for this sort of
project, but if you want one, I can put one together for you.
Client project manager to vendor sales rep: Get this idiot out of here!
When the vendor project manager is strong and the client project manager is
weak, it's an opportunity for skills transfer -- a benefit beyond the project
deliverables.
Meanwhile, regardless of the client project manager's strength, the vendor
project manager has an inside partner to help navigate company politics, provide
insights into How Things Work Around Here, cajole internal project participants
to show up, and so on.
The one-or-the-other debate is just a false dichotomy. Both is far better than
either.
- Bob